It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

What is unusual about the speech hamlet begins to recite?
Why do graphs of proportional relationships pass through the origin?
Can I get help on this
I NEED HELP DONT DO IT FOR ME JUST HELP ME ILL GIVE BRAINLESS For this assignment, use the novel or short story( Rikki Tikki Tavi ) you chose to read for Modu
I NEED HELP ASAP In what way does Koch's procedure demonstrate the use of the scientific method?
Blank is mantaining stable conditions inside the body
a basic concept in economic is that all resources area) scare b) allocated c) valuabled) renewable
On hot sunny days, tire should not be over-inflated,why?
Can someone help me with these ?
what is equal to 2/3