15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

im feeling nice today who ever answer this question gets brainliest its a realllllly hard question only if 2 people answer what ever one is correct gets it and
Many poor Europeans were drawn to colonies in the Americas because?
What happens to the force of gravity between two masses if one mass is decreased? A. It increases. B. It fluctuates. C. It decreases. D. It stays the same. Just
A line passes through the points (–10, –10) and (–5, –10). What is its equation in slope-intercept form?
Find the value of 2 over 3 divided by 6
What result did Britain's war with France have on the colonies?
1. En que se basan los filósofos griegos del siglo V antes de Cristo el porqué de la vida y el orden del mundo? 2. ¿Por qué la filosofía es una ciencia muy comp
a^2-b^2 a^2b-ab^2-------------- ÷ ---------------a^2b+ab^2 a^2b- ab^2​
9/n+2=2/6 How do I solve for n?
Evaluate the impact of risky behavior on your personal which expectations in relation to the career l follow as being a doctor​